• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Eyemouth Harbour Trust

Eyemouth Harbour Trust

Scotland's first port of call...

  • Location
    • Access & Facilities
    • Navigation
    • Arriving at Eyemouth: visiting vessels
  • About the Harbour
    • Brief History
    • The Harbour Trust
      • Meet our Trustees
      • Meet the Team
    • Notices to Mariners
    • Port Marine Safety Code
      • Port Waste Management Plan
      • Marine Safety Plan
      • Oil Spill Contingency Plan
    • Working at Eyemouth Harbour [contractors]
    • Harbour Projects
    • Protecting the Marine Environment
    • Office Facilities
    • Gallery
    • Videos
  • Marine Sectors
    • Fishing
      • Ice production facility
    • Leisure Craft
    • Offshore Wind
    • Cruise
    • Leisure Activities
  • News & Events
  • Surrounding Area
  • Contact Us

Various Works at Eyemouth Harbour – w/c 7th December 2020

Various contractors are currently on site and works are now underway around the harbour office building and Gunsgreen quayside, from w/c 7th December through into the New Year.

Access to parking around the building and the quayside areas will be restricted during this time; alternative parking is available at the Scottish Borders Council long stay car park at Gunsgreenhill.  Various areas will be fenced off for safety, and to enable contractors to work unhindered.   Space for day to day operational requirements; (fishing activity, landing, fuel and ice) has been set aside.

Works include:

  • Installation of new fuel facility on Gunsgreen Quay, between the harbour office building and Gunsgreen House. This includes tank & fuel facility installation and commissioning for approx. 2 weeks.
  • Relocation of electrical supplies (north end of the harbour building, behind the harbour building and along to the new fuel tank location) for approx. 5 weeks.
  • New dive shore car park access to the north of the harbour building. Re-routing of the dive shore road (off road hammerhead) to join existing road. As the contractor is having to secure the entire site, there will be no vehicular access to the dive shore car park for approx. 8-10 weeks. There will still be pedestrian access to the site and coastal path. Works are expected to take approx. 8-10 weeks.

The public & visitors are urged to take extra care around the Gunsgreen area of the harbour and adhere to all safety signs & notices during these works. 

Any queries, please contact the Harbour Master & Operations Team on 018907 50223 / Mobile: 07885 742505

Posted: 8/12/20

Primary Sidebar

Site Search

Latest News & Events

Annual General Meeting

Eyemouth Harbour Annual General Meeting The Annual General Meeting of Eyemouth Harbour Trust will be held on … [Read More...] about Annual General Meeting

View more news & events...

Follow us on:

Facebook Twitter Instagram

Footer

Location
About the Harbour
Access & Facilities
News & Events
Surrounding Area
Contact Us

Follow us on:

  • Facebook
  • Instagram
  • Twitter
  • Vimeo
Privacy and Policies Copyright © 2025 Eyemouth Harbour Trust
Harbour Office, Gunsgreen Basin, Eyemouth, TD14 5SD • Tel: 01890 752494